- 11,000 SF, 10-bay Vehicle Storage Facility including admin bay, sand shed, wash bays, and 5-tank mag-chloride containment system
- Water and drainage systems: wash bays served by a reclaimed water system using well water, with interior trench drains connecting to four underground interceptor tanks
- 360 Engineering provided mechanical and plumbing engineering design in collaboration with VEGA Architecture
- Fast-Track Delivery: Completed design on an accelerated schedule—4 weeks to 65% CDs, 3 weeks to 85%, and 2 weeks to 99% permit drawings
- Site-specific adaptation: CDOT template drawings and specifications were utilized to customize the design for the site’s size, orientation, and existing well water supply