- 32,000 SF Scotty’s Castle campus, a historic site with multiple buildings storing artifacts and open for tours, damaged by a 2015 flash flood that impacted underground infrastructure and interior spaces
- 360 Engineering evaluated and designed mechanical systems, including a chilled water and heating water system with fan coil units, to maintain strict temperature and humidity controls for artifact preservation
- Central Utility Plant (CUP): developed a campus-wide CUP concept to serve multiple buildings, reduce maintenance costs, support sustainable operations, and guide phased implementation
- Master planning and phasing: created a Master Plan outlining phased upgrades based on funding and operational priorities, with ongoing design work for additional buildings like the Long Shed
- Commissioning and performance: provided independent commissioning services to verify that all systems met design intent and owner requirements upon installation