- 190,000 SF, three-story tenant finish to accommodate rapid company growth, second Crocs headquarters 360 Engineering provided mechanical and plumbing engineering services
- Existing Variable Air Volume (VAV) air-handling units, medium-pressure ductwork, and multiple VAV boxes with hydronic reheat were strategically reused to control cost and minimize disruption while meeting new layout and performance requirements
- A key challenge was transforming a traditional 2000’s office with lay-in ceilings into Crocs’ preferred open, industrial-style workspace with exposed structure and ductwork
- New ductwork layouts and air device locations were carefully coordinated to be both functional and visually intentional, as all systems would be exposed to occupants
- Acoustic performance was a key design consideration, requiring thoughtful coordination to balance comfort, noise control, and architectural intent