- 53,000 SF school retrofit to improve ventilation and add air conditioning, led by 360 Engineering as the Prime Consultant
- Assessment of complex legacy systems: mezzanine Air Handling Units (AHUs), unit ventilators, and terminal boxes
- Mechanical system strategy shift from mezzanine AHUs to rooftop units for efficiency and maintenance access
- Packaged heat pump Rooftop Units (RTUs) with energy recovery and gas backup aligned with DPS electrification and GHG reduction goals
- Cost and vendor coordination during Design Development to evaluate RTU options
- RTU placement optimized to minimize structural impacts and construction cost
- Electrical and utility coordination with DPS, Xcel Energy, electrical engineers, and CMGC to replace switchgear and address equipment lead times